Construction joint between precast panels
Overall view of construction site
Temporary bracing connection to ground via plate and bolts
U beam/ column connection to ground
here they are placing a new layer of support and scaffolding getting ready for pouring the second floor slab
Temporary bracing connection to ground via plate and bolts
Overall view of construction site
Week 7 case study
Huntingdale
railway parade construction site.